ISLAMABAD, Oct 30: The Civil Aviation Authority (CAA) on Tuesday said it was acquiring another 4,000 kanals of land at the site of the under-construction New Islamabad International Airport (NIIA) to build a second runway.

The original plan had a main and an emergency runway, however, it dawned upon the CAA management at a much later stage that they needed to build another runway to make the airport compatible with international standards.

Briefing mediapersons about the progress of the project, CAA Director Planning and Development Vikram Soda said that the process of land acquisition had been initiated through the Punjab government.

The cost of land was fixed at about Rs0.56 million per kanal. Owners would be getting additional amount for any construction on their land, he added.

The new airport is being built in Pind Ranja near Fatehjang. Some 3,500 acres of land had already been acquired for the project expected to cost Rs35 billion.

The earlier land acquisition process that continued for about a couple of decades was marred by allegations of corruption and favouritism. It had been alleged that CAA had violated the Land Acquisition Act, 1894, while acquiring some additional chunks of land during the first phase.

The runways being constructed at the airport, Mr Soda said, would be of Category E — capable of handling even the most modern aircraft like the recently launched A-380.

The CAA official claimed that the site preparation work was on course and 54 per cent of it had been completed since the project took off in April this year. He hoped that the contractors would be able to complete the site preparation ahead of their scheduled completion date of February 2008.

About the progress on design preparations for what is being billed as the most modern and state-of-the-art airport in the region, Mr Doda said that preliminary design had been prepared, which would be finalised in three months.

CAA has decided to divide the construction contract into two packages.

The contract for the first package comprising airside works would be awarded in January next with a completion time of 24 months. The second package contract, which included construction of terminal building and the ancillary structures, would be awarded in February 2008, which would take 30 months to complete.

Brushing aside concerns about the financial viability of the project, CAA Director-General Farooq Rehmatullah said that the payback period for the new airport project is estimated to be 10- 12 years, which is good according to the industry standards.

Opinion

Editorial

Digital growth
Updated 25 Apr, 2024

Digital growth

Democratising digital development will catalyse a rapid, if not immediate, improvement in human development indicators for the underserved segments of the Pakistani citizenry.
Nikah rights
25 Apr, 2024

Nikah rights

THE Supreme Court recently delivered a judgement championing the rights of women within a marriage. The ruling...
Campus crackdowns
25 Apr, 2024

Campus crackdowns

WHILE most Western governments have either been gladly facilitating Israel’s genocidal war in Gaza, or meekly...
Ties with Tehran
Updated 24 Apr, 2024

Ties with Tehran

Tomorrow, if ties between Washington and Beijing nosedive, and the US asks Pakistan to reconsider CPEC, will we comply?
Working together
24 Apr, 2024

Working together

PAKISTAN’S democracy seems adrift, and no one understands this better than our politicians. The system has gone...
Farmers’ anxiety
24 Apr, 2024

Farmers’ anxiety

WHEAT prices in Punjab have plummeted far below the minimum support price owing to a bumper harvest, reckless...