KARACHI: Lucky Electric Power has decided to use indigenous coal from Thar for power generation at its 660-megawatt Port Qasim plant, which is likely to achieve financial close by March 2017 and commence commercial operations by December 2019.

This will make it the first power plant in the country to use Thar lignite (coal) away from the mine mouth.

Although the project was originally based on imported coal, it was converted to indigenous coal resources in line with the national policy of reducing reliance on imported coal.

Lucky Electric Power, a wholly owned subsidiary of Lucky Cement, is being set up at an estimated project cost of $850 million.

Talking to a group of journalists, CFO Naeem Kasbati said the company has already obtained required approvals, including the letter of support and National Electric Power Regulatory Authority (Nepra) upfront tariff. It has also leased 250 acres of land close to Port Qasim.

Mr Kasbati said the 660MW coal power plant of Lucky Electric Power is based on supercritical technology to ensure the highest efficiency level and reduce emissions. It may be noted that mine-mouth power projects under construction in Thar are using subcritical technology.

Responding to a question, Mr Kasbati said it is false that Thar lignite (coal) can only be used at the mine mouth by power plants, adding that his company hired renowned experts to ensure that Thar coal was equally good for power generation away from the mine mouth.

He said the company selected one of the most feasible sites for the power plant in terms of power evacuation, availability of abundant cooling water, fuel supply chain, proximity to the industrial area and distance from the main city.

Lucky Electric Power has done due diligence of Thar coal for its use in the power plant and is now formalising a coal supply agreement with Sindh Engro Coal Mining Company. An agreement for sustainable coal supply will be finalised by the end of this month, he noted.

Published in Dawn, November 16th, 2016

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Enter the deputy PM

Enter the deputy PM

Clearly, something has changed since for this step to have been taken and there are shifts in the balance of power within.

Editorial

All this talk
Updated 30 Apr, 2024

All this talk

The other parties are equally legitimate stakeholders in the country’s political future, and it must give them due consideration.
Monetary policy
30 Apr, 2024

Monetary policy

ALIGNING its decision with the trend in developed economies, the State Bank has acted wisely by holding its key...
Meaningless appointment
30 Apr, 2024

Meaningless appointment

THE PML-N’s policy of ‘family first’ has once again triggered criticism. The party’s latest move in this...
Weathering the storm
Updated 29 Apr, 2024

Weathering the storm

Let 2024 be the year when we all proactively ensure that our communities are safeguarded and that the future is secure against the inevitable next storm.
Afghan repatriation
29 Apr, 2024

Afghan repatriation

COMPARED to the roughshod manner in which the caretaker set-up dealt with the issue, the elected government seems a...
Trying harder
29 Apr, 2024

Trying harder

IT is a relief that Pakistan managed to salvage some pride. Pakistan had taken the lead, then fell behind before...