KARACHI, July 28: The City Government, Lyari Town Administration and the National Highway Authority (NHA) on Monday began draining out rain water from Mauripur road apart from cleaning storm water drains passing through Lyari.

The construction of the Northern Bypass has affected the disposal of rain water from certain areas of Lyari town as a result of which water is still seen accumulated on roads.

In order to initiate immediate steps, the DCO Karachi Mir Hussain Ali held a meeting which was attended by Project Director NHA, Town Nazim Abdul Khaliq Jumma, TMO and officers concerned of the city government.

In the meeting it was decided that during the construction phase of the Northern Bypass, care would be taken to keep the storm water drains passing from Lyari town unaffected and to find a permanent solution to the problem.—APP

Opinion

Editorial

Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....
Soft on traders
08 Jun, 2026

Soft on traders

THE Fixed Tax Asaan Scheme for traders with an annual turnover of up to Rs200m has been designed as a ‘pragmatic...
Ceasefire in name
Updated 08 Jun, 2026

Ceasefire in name

Both sides accuse the other of violating the truce that was supposed to halt the conflict in April, yet neither appears willing to abandon negotiations altogether.
Damaged childhoods
08 Jun, 2026

Damaged childhoods

CHILD abuse is so prevalent that the UN ranked Pakistan as the least safe country for children. Even so, more than...