ISLAMABAD: The Water and Power Development Authority (Wapda) on Thursday awarded a $354.6 million worth of contract to Power Construction Corporation of China Ltd (PCCCL) for civil works of the 1,530MW Tarbela 5th Extension Hydropower Project after completion of an international competitive bidding process.

The contract was signed by Project Director Tarbela 5th Extension Project Muhammad Azam Joya and PCCCL Executive Representative in Pakistan Ling Jianke. The signing ceremony was also attended by Wapda Chairman Muzammil Hussain, World Bank Country Director Najy Benhassine, World Bank Task Team Leader Dr Rickard Liden, Wapda Member Finance Naveed Asghar, Member Water Abdul Zahir Khan Durrani, Member Power Jamil Akhtar, General Managers concerned and representatives of the project consultants.

The contract involves modification of tunnel-5, raised intake, power house, tailrace works including channel and culverts and penstocks. The project will be fully completed in 37 months with first unit coming into production by end-May 2024, followed by second unit by end-June and third unit by end-July 2024.

The 5th extension project is being constructed on tunnel no. 5 of Tarbela dam with approved PC-1 cost of $807 million (Rs82.36bn). International Bank for Recons­truction and Development (IBRD), World Bank is providing $390m, while Asian Infrastructure Invest­ment Bank (AIIB) to give $300m loan. Cumulative generation capacity of the project would be 1,530MW with three generating units of 510MW each.

The project is scheduled to start generation by mid-2024 and will provide 1.347 billion units to the national grid every year. Upon its completion, Tarbela dam’s power generation potential would stand fully harnessed its installed capacity of 4,888MW at present to 6,418MW.

Published in Dawn, May 7th, 2021

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Editorial

31 Jul, 2026

Expanding conflict

WITH neither of the belligerents willing to back down, and the theatre of conflict expanding geographically, the...
31 Jul, 2026

Spoils and spats

A FIGHT over assembly seats in Azad Jammu and Kashmir has laid bare what seem to be some deep resentments between ...
31 Jul, 2026

Unfair tax system

THE disclosure that the FBR collected nearly Rs1.9tr in sales and income taxes through electricity bills over the...
30 Jul, 2026

Debt that stays

THE power sector’s circular debt grew by Rs61bn in the last fiscal year, taking the total to roughly Rs1.67tr from...
30 Jul, 2026

HIV warning

THE HIV infections detected around two SESSI-run hospitals in Karachi demand far more than another hurried committee...
30 Jul, 2026

End trafficking

MODERN slavery, in the form of human trafficking, is among the state’s gravest failures. Scores of Pakistanis are...