Public park construction lingers for six years

Published
0
_Dawn
_Dawn

NAROWAL: The construction of Prem Nagar Public Park, initiated in 2017 with an allocation of Rs15 million from local government funds, remains incomplete after six years.

Land dispute litigation and a lack of interest from Sialkot district administration and local government officials have plagued the project. The allocated funds lapsed three times, hindering progress.

The construction of the park, located in the middle of Sialkot city, started on a drive by the local residents. Soon after the start of the work, eight people claimed ownership of the land, and got a court order halting construction. By that time, Rs7.5 million had already been spent on the park’s boundary wall.

Residents also decided to fight for the land acquisition, and engaged in a legal battle with the district administration of Sialkot.

Muzamil Ali Silharia, a resident and businessman, recounts the battle by the local residents against the ‘influential local residents’ attempting to seize government land forcibly.

He said the local residents submitted 550 requests across various platforms, such as the Supreme Court of Pakistan, Lahore High Court, president of Pakistan, prime minister, chief minister, chief secretary, Gujranwala commissioner, and deputy commissioner of Sialkot to settle the land dispute and start the construction of the Prem Nagar Public park. In 2020, the court settled the land dispute, allocating four kanals to the litigants and 16 kanals for the park.

Mr Silharia said that despite the government’s re-release of Rs7.5 million in 2020 to complete construction, the alleged disinterest of the district administration, local government, and deputy director of development led to the funds lapsing. Funds allocated for the park in 2021 and 2022 also remained unused.

In 2023, the Punjab government earmarked Rs7.5 million in the annual development funds for Prem Nagar Park. However, no progress has been observed at the site. Mr Silharia accused the deputy commissioner and executive engineer (EXEN) of the local government of causing delays. The construction remained a distant dream despite the National Commission of Human Rights ordered the park’s construction.

Residents like Aamir Chaudhry said Prem Nagar Park would be the sole recreational space for 600,000 residents of Mohalla Prem Nagar, Nasir Road, and Mohalla Islamia Park. The absence of alternative parks or grounds nearby leaves children and women with limited options for leisure activities.

He said the nearest parks, Fatima Jinnah Park and Gulshan Iqbal Park, are located five and 12 kilometers away. Mirza Salim, another local resident, drew attention to the deteriorating conditions of Prem Nagar Park. He described the presence of massive piles of grass, bushes, stones, and garbage, creating an unpleasant environment, especially during the rainy season when a strong smell emanates from the park. He said that the construction site, filled with dirt, becomes a breeding ground for flies, mosquitoes, poisonous insects, and snakes.

The National Commission of Human Rights has also ordered the construction of the park. However, the government has not taken any action yet.

The residents of Prem Nagar are now planning to hold protests to demand the completion of the park.

Local Government EXEN Muhammad Nasir said that he will re-tender after taking permission from the Election Commission of Pajistan. He said that the construction of the park will be completed soon with annual development funds.

Mohammad Atif, deputy director, said that the Punjab government has provided funds to complete the construction of the park. He said that the legal process is ongoing for the completion of the project. Newspaper advertisement for tender will be published soon.

Published in Dawn, November 25th, 2023

Opinion

Editorial

Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...
Terror and politics
Updated 29 Sep, 2026

Terror and politics

There is an urgent need to tone down the rhetoric and tackle terrorism as a collective challenge for both the affected provinces and the federation.
Watching the glaciers
29 Sep, 2026

Watching the glaciers

THE latest signs from Pakistan’s mountains are worrying. Suparco says the number of unfrozen glacial lakes it...
Dangerous agenda
29 Sep, 2026

Dangerous agenda

AS the world remains fixated on the US-Iran conflict, elsewhere in the Middle East, Israel is consolidating its grip...