No further extension in Sukkur Barrage rehabilitation project: WB official

Published November 3, 2023
WORLD Bank officials, in the front row, listen to chief engineer of Sukkur Barrage.—Photo by the writer
WORLD Bank officials, in the front row, listen to chief engineer of Sukkur Barrage.—Photo by the writer

SUKKUR: World Bank’s water resources management specialist Theruni Liyanage has urged the need to complete rehabilitation and modernisation of Sukkur Barrage in its stipulated period of four years, clearly stating that no further extension will be granted.

She was part of the World Bank Implemention Support Mission which reviewed the work progress of the barrage on Thursday, led by WB practice manager Mr Josses Mugabi.

Briefing the mission on the occasion, Sukkur Barrage Chief Engineer Syed Sardar Ali Shah suggested that a trail gate without counter weight should be installed at the weir instead of the pocket before the flood season as “we can observe the operation of the trail gate without counter weight of 80 tonne to reduce the extra load on the barrage”.

Sindh Barrages Improvement Project (SBIP) Deputy Director Abdul Razak Memon said the provision of the trail gate for physical demonstration had already been kept in the scope of the rehabilitation and modernisation of the Sukkur Barrage contract.

Ms Liyanage, who is also co-task team leader of the WB, said that it had been observed that the progress of the work of Sukkur barrage was continued according to the proper schedule.

She advised that there was also need to improve the health, safety environment.

Mr Mugabi said the methodology of the rehabilitation of Sukkur Barrage was organised, but it needed strengthening of the weaknesses.

He said that according to the suggestion and guidelines of a panel of experts and departments’ technical personnel and international consultants, the design work of the barrage was in progress.

The World Bank mission also visited the Indus Blind Dolphins Center, and ongoing construction works related to the SBIP, including the mechanical workshop and engineering works.

Those who accompanied the team included Coordination and Monitoring Unit of Planing and Development’s Project Coordi-nator Nazir Essani, Sociologist Ghulam Hyder Qureshi, Director Ghulam Murtaza Abro and others.

Published in Dawn, November 3rd, 2023

Opinion

Editorial

Water vision
01 May, 2026

Water vision

WATER insecurity in Pakistan has been building up for decades as per capita water availability has declined from...
Vaccine policy
01 May, 2026

Vaccine policy

PAKISTAN has finally approved its first National Vaccine Policy; a step the health ministry has rightly described as...
Labour rights
Updated 01 May, 2026

Labour rights

THE annual observance of May Day should move beyond statements about the state’s commitment to the rights of...
UAE’s Opec exit
Updated 30 Apr, 2026

UAE’s Opec exit

THE UAE’s exit from Opec is another sign of the major geopolitical shifts that are reshaping the global order. One...
Uncertain recovery
30 Apr, 2026

Uncertain recovery

PAKISTAN’S growth projections for the current fiscal present a cautiously hopeful picture, though geopolitical...
Police ‘encounters’
30 Apr, 2026

Police ‘encounters’

THE killing of nine suspects by Punjab’s Crime Control Department across Lahore, Sahiwal and Toba Tek Singh ...