SC tells govt to ensure payment of dams’ dues to Wapda

Published February 13, 2020
The Supreme Court on Wednesday ordered the secretary of power to ensure payment of dues to Wapda in a year by adhering to the payment schedule for construction of Diamer-Bhasha and Mohmand Dams. — AFP/File
The Supreme Court on Wednesday ordered the secretary of power to ensure payment of dues to Wapda in a year by adhering to the payment schedule for construction of Diamer-Bhasha and Mohmand Dams. — AFP/File

ISLAMABAD: The Supreme Court on Wednesday ordered the secretary of power to ensure payment of dues to Wapda in a year by adhering to the payment schedule for construction of Diamer-Bhasha and Mohmand Dams.

“Is it not your duty that the money be paid to Wapda?” Chief Justice Gulzar Ahmed inquired from Power Secretary Irfan Ali and dictated an order that the latter would strictly comply with orders of the Supreme Court and would not obstruct in a matter that may delay payments.

The chief justice was heading a five-judge implementation bench of the Supreme Court which had taken up the Diamer-Bhasha - Mohmand Dams Funds case.

Wapda Chairman Muzzamil Hussain told the Supreme Court that the authority still had to get the promised money of Rs35 billion and Rs17bn, respectively, for Diamer-Bhasha and Mohmand Dams.

The chairman also informed the court that the revised PC-1 of the resettlement plan to rehabilitate the people displaced by the construction of the Diamer-Bhasha Dam was pending approval at the ECNEC.

Additional Attorney General Khurram Saeed, however, assured the court that the revised PC-1 would be taken up by ECNEC as early as possible, preferably in two weeks.

The court, however, asked Wapda to furnish a breakdown of Rs1.8bn required to provide security at the Mohmand Dam site. Details must include both the capital cost as well as the recurring cost.

Executive Director of State Bank of Pakistan Mohammad Ali Malik informed the court that instructions had been passed on to all branches of commercial banks as well as the Pakistani missions to ensure transmission of the collection of funds for the dam. He said that over the last two weeks Rs25.5 million had been collected for the dam funds.

At the hearing on Dec 12, 2019, the Supreme Court was told that the funds collected through the dam funds had been invested in three months Government of Pakistan Treasury Bills and up to Dec 11, 2019, the amount so generated was Rs11bn on which a profit of Rs692m was earned to make the total funds at Rs12bn. The case will now be taken up after a month.

Published in Dawn, February 13th, 2020

Opinion

Editorial

Immunity gap
Updated 26 Apr, 2026

Immunity gap

Pakistan’s Big Catch-Up campaign showed progress but also exposed the scale of gaps in routine immunisation.
Danger on repeat
26 Apr, 2026

Danger on repeat

DISASTERS have typically been framed as acts of nature. Of late, they look increasingly like tests of preparedness...
Loose lips
26 Apr, 2026

Loose lips

PAKISTANIS have by now gained something of an international reputation for their gallows humour, but it seems that...
Lebanon truce
Updated 25 Apr, 2026

Lebanon truce

THE fact that the truce between Israel and Lebanon has been extended for three weeks should be welcomed. But there...
Terrorism again
25 Apr, 2026

Terrorism again

THE elimination of 22 terrorists in an intelligence-based operation in Khyber highlights both the scale and ...
Taxing technology
25 Apr, 2026

Taxing technology

THE recent decision by the FBR’s Directorate General of Customs Valuation to increase the ‘assessed value’ of...