LAHORE: Water and Power Development Authority (Wapda) Chairman retired Lt Gen Muzammil Hussain says 1,410MW Tarbela 4th Extension Hydropower Project will complete in a phased manner from February to May 2018.

“We are confi dent to complete Tarbela 4th Extension Hydropower Project in a phased manner from February 2018 to May 2018,” he said in a meeting with the senior project offi - cials during his visit to the site on Saturday.

However, he added, the steady efforts on the part of the project management, including the consultants and the contractors, were needed to meet the timeline vis-à-vis implementation of the project.

“I hope the project management would put in their maximum for the purpose,” he said.

Earlier, Mr Hussain reviewed construction progress on various components of the project, including intake structure, powerhouse, switch yard etc.

The project authorities and representatives of the consultants and the contractors briefed the Wapda chairman on the progress achieved so far on civil and electromechanical works of the project.

Detailed deliberations were also made about the steps to meet challenges faced by the project during the visit.

The project is a component of leastcost energy generation plan, which is being implemented by Wapda.

Under Tarbela 4th Extension Project, three generating units – each having capacity of 470MW – are being installed at Tunnel No.4 of Tarbela Dam.

With completion of the project, generation capacity of Tarbela Hydel Power Station will increase to 4,888MW from the existing 3,478MW.

Published in Dawn, July 2nd, 2017

Opinion

Editorial

Budget presser
Updated 14 Jun, 2026

Budget presser

If the FBR falters, the government will find itself in hot water sooner rather than later.
Muharram precautions
14 Jun, 2026

Muharram precautions

WITH Muharram due to start next week, the authorities have already begun annual exercises to ensure that the ...
Blood bequests
14 Jun, 2026

Blood bequests

WORLD Blood Donor Day offers a moment of “gratitude, advocacy and renewed commitment” for thalassaemia patients...
Sustainable path?
Updated 13 Jun, 2026

Sustainable path?

The FY27 budget is the first clear signal that the government is ready to transition from stabilisation to growth.
Prioritising education
13 Jun, 2026

Prioritising education

THOUGH the improvement in the country’s literacy rate may be slight, as highlighted by the Economic Survey, it ...
Poverty’s rise
13 Jun, 2026

Poverty’s rise

AS attention turns to the government’s plans for the coming fiscal year, one set of figures deserves particular...