Resentment over delay in road project

Published
0

KOHAT, Dec 20: Public representatives, business community and transporters have expressed resentment over the delay in the completion of a 35-km-long section of the Kohat-Rawalpindi Road despite repeated warnings by the governor to the Frontier Highway Authority, and demanded that the contractor should be changed.

In a press release issued here on Saturday, Qalbe Hassan and Shaukat Habib, MPAs, asked the government to cancel the contract. They said the contractor did not have technical know-how to manage such an important project as well as the machinery required to execute the work.

The provincial governor had ordered the widening of the Rawalpindi Road from Cavagnari House to Gumbat which was to be completed by September 2003. However, the contractor has been unable to complete even 40 per cent of the work as yet.

It has been learnt that the contractor, M/s Faisal Construction Company, had complained that the FHA was not providing him with the machinery and Pesco was not cooperating with him in removal of electricity poles that had been affecting the pace of work. He had informed the government early this year that the project would be delayed by six months.

The governor, who inspected the project in October, had issued orders to the Pesco chief to immediately remove the poles and suspended an FHA official.

The poles have been removed but even then the work has been continuing at a snail’s pace for unknown reasons and the contractor says that the work will now be completed at the end of the next year.

Opinion

Editorial

Expanding conflict
31 Jul, 2026

Expanding conflict

WITH neither of the belligerents willing to back down, and the theatre of conflict expanding geographically, the...
Spoils and spats
31 Jul, 2026

Spoils and spats

A FIGHT over assembly seats in Azad Jammu and Kashmir has laid bare what seem to be some deep resentments between ...
Unfair tax system
31 Jul, 2026

Unfair tax system

THE disclosure that the FBR collected nearly Rs1.9tr in sales and income taxes through electricity bills over the...
Debt that stays
30 Jul, 2026

Debt that stays

THE power sector’s circular debt grew by Rs61bn in the last fiscal year, taking the total to roughly Rs1.67tr from...
HIV warning
30 Jul, 2026

HIV warning

THE HIV infections detected around two SESSI-run hospitals in Karachi demand far more than another hurried committee...
End trafficking
30 Jul, 2026

End trafficking

MODERN slavery, in the form of human trafficking, is among the state’s gravest failures. Scores of Pakistanis are...