PESHAWAR, Aug 6: A heavy power transformer of National Transmission and Dispatch Company at Mardan developed a major fault on Monday leaving a large number of power consumers in several parts of Khyber Pakhtunkhwa without power.

“A 160mba transformer of NTDC’s 220kv grid station at Mardan developed a major technical fault, rendering it non-functional,” said a relevant official. As a result, a large number of power consumers in Nowshera, Mardan, Chakdarra, Dargai, Jalala, and a few other areas would suffer power outages longer than usual hours of loadshedding for next few days, said the official.

“Technical staff is working to restore the transformer,” said Shaukat Afzal, a spokesman of Pesco. He said it would take a couple of days to remove the fault.

However, another official said the repair work would take about one week to make the transformer functional.

Opinion

Editorial

IMF’s unease
Updated 24 May, 2024

IMF’s unease

It is clear that the next phase of economic stabilisation will be very tough for most of the population.
Belated recognition
24 May, 2024

Belated recognition

WITH Wednesday’s announcement by three European states that they intend to recognise Palestine as a state later...
App for GBV survivors
24 May, 2024

App for GBV survivors

GENDER-based violence is caught between two worlds: one sees it as a crime, the other as ‘convention’. The ...
Energy inflation
Updated 23 May, 2024

Energy inflation

The widening gap between the haves and have-nots is already tearing apart Pakistan’s social fabric.
Culture of violence
23 May, 2024

Culture of violence

WHILE political differences are part of the democratic process, there can be no justification for such disagreements...
Flooding threats
23 May, 2024

Flooding threats

WITH temperatures in GB and KP forecasted to be four to six degrees higher than normal this week, the threat of...