KARACHI: After suffering a month-long delay due to some ‘unavoidable’ reasons, the first phase of the Bus Rapid Transit System (BRTS) — Green Line and Orange Line — in Karachi is likely to begin by the middle of December, it emerged on Thursday.

Officials associated with the project said the BRTS-I would ‘revolutionise’ the city’s existing transport system on completion after a year.

Sources said the Orange Line project, which was planned to be launched in the first week of November, could not go as per plan, as the offers received from the bidding companies were ‘extremely impracticable’.

They said the lowest bid for the Orange Line was Rs2.2 billion, which was 80 per cent more expensive than (Rs1.3 billion) what the government consultant, Nespak, had recommended.

It was for this reason that delayed the project compelling the authorities concerned to seek fresh bids for the project, the sources said, adding that the bidding would be made this month again.

At the same time, they said, the provincial government had paid Rs200 million to the Karachi Water and Sewerage Board, Sui Southern Gas Company Limited, PTCL and the National Telecommunication Corporation (NTC) for relocation of their utilities along the route of the Orange Line.

The sources said the utilities would complete relocation within two months during which the government would complete its process of rebidding. Once the relocation was done, the successful bidder would start its work and complete it by the end of next year, they said.

Orange Line will connect Orangi to the Board Office, Nazimabad, with the route of the Green Line, a project being commenced by the federal government, according to the officials.

Greeen Line

They said the Green Line project, too, would begin in the mid of December.

Green Line is a 17-km project linking Surjani and Gurumandir. It will cost Rs16.85 billion, which included a substantial elevated portion between Buffer Zone and the Lasbella intersection.

Yellow Line

The officials said the provincial government had decided to award the Rs18 billion Yellow Line project to a Chinese company, CUEC, though a formal deal of the public-private project was yet to be signed.

The 26.5-km-long project will connect Jam Sadiq Ali Bridge in Korangi Industrial Area to Saddar via Korangi Road, FTC, Sharea Faisal, Shahrah-i-Qaideen and culminate at the Preedi Street near the Parking Plaza, Saddar.

The officials said the Sindh government would put in a share of 14pc, while the CUEC’s share would be 16pc and the rest would be loan provided by the Chinese government. The project will be completed within two years after signing of the deal.

Published in Dawn, December 4th, 2015

Opinion

Editorial

Battling hate
Updated 15 Mar, 2026

Battling hate

In the current scenario, geopolitical conflict, racial prejudice and religious bigotry all contribute to the threats Muslims face.
TB drugs shortage
15 Mar, 2026

TB drugs shortage

‘CRIMINAL negligence’ is the phrase that jumps to mind when one considers the disturbing consequences of the...
Chinese diplomacy
Updated 14 Mar, 2026

Chinese diplomacy

THERE are signs that China is taking a more active role in trying to resolve the issue of cross-border terrorism...
Fragile gains at risk
14 Mar, 2026

Fragile gains at risk

PAKISTAN is confronting an external shock stemming from the US-Israel war on Iran that few of the other affected...
Kidney disease
14 Mar, 2026

Kidney disease

ON World Kidney Day this past Thursday, the Pakistan Medical Association raised the alarm on Pakistan’s...
Delicate balance
Updated 13 Mar, 2026

Delicate balance

PAKISTAN has to maintain a delicate balance where the geopolitics of the US-Israeli aggression against Iran are...