Federal Minister for Water and Power Raja Parvez Ashraf visiting after inaugurating 100KV Reshma Power Plant at Raiwind Lahore on Saturday. – Photo by APP

LAHORE: In a bold bid to favour a rental plant, Water and Power Minister Raja Pervez Ashraf on Saturday inaugurated a plant near Lahore, ignoring that the company had failed to meet the deadline by a year and hence “it is a ripe case for slapping penalties, renegotiating tariff, reducing the rental terms and even cancellation of the contract”.

The 201MW Reshma Power plant is the second most expensive plant after Karachi’s ship-mounted Karkey Elek Trik Uretim of Turkey (5.98 cents per unit) and will cost the country 4.97 cent per unit, excluding oil price.

According to calculations by independent experts, each unit will cost around Rs16, possibly leading to a rise in tariff by 2.30 per cent throughout the country.

The contractual terms between the Pakistan Electric Power Company (Pepco) and the Reshma Power clearly provide all four options — slapping liquidated damages (LDs), reducing term of rental contract by a year (corresponding to the delay), renegotiating the tariff and even cancelling the entire contract.

With the minister sanctifying the plant by inaugurating it, Pepco seems to have lost an opportunity to renegotiate the rental service agreement (RSA) and possibly reduce the extremely high tariff rates.

The plant had to be online by the end of 2009, the deadline given by the minister to end loadshedding in the country, but it is not fully operational as yet. According to the contract, Pepco can now take the charge of the situation.

The haste with which the minister went to inaugurate the 201MW plant can be gauged from the fact that it has only one of four machines (50MW each) up and that too on a test run. The plant has still not achieved even 10 per cent of generation capacity.

The inauguration also flies in the face of the cabinet decision of Jan 27 last year, which requires strict enforcement of contract time lines as formalised in the rental service agreements.

Reshma Power came out of the bidding in late 2008 and the PPIB board approved it on April 9, 2009.

According to details available on the PPIB’s website and the copy of the RSA available with Dawn, the plant was to be provided seven per cent mobilisation advance. Instead, the ministry of water and power directed Pepco to change the terms and double (14 per cent) the advance payment — amounting to $55.26 million (Rs4.576bn) — and it was done accordingly.

According to the RSA signed in September 2009: “In case the seller (RPP) fails to complete the project within cure (stipulated) period of 30 days after the

targeted COD and thereafter, the seller will be charged at the rate of $191 per day per megawatt up to a maximum amount equivalent to $17,190 per megawatt for a delay of up to three months after cure period. Such amount will be charged from first rental payment of the monthly rental service fee. If achievement of commercial operations date (COD) is further delayed due to the seller, the buyer shall have the right to renegotiate the contract.”

Now instead of renegotiating the project which has failed to achieve COD for nearly a year, and still counting, the ministry and Pepco looked to be in an “accommodating mode.”

When contacted, a spokesman of the Ministry of Water and Power claimed: “All rental plants got delayed for reasons, like third party audit by the Asian Development Bank, that were beyond their control. Reshma Power is no exception. As far as the contractual obligations are concerned, it is for Pepco to ensure them all.”

A Pepco spokesman maintained: “All decisions will be taken in line with the contractual obligations.”

The owner of Reshma Power neither responded to repeated calls and messages left on his cellphone nor he asked his spokesman to issue their version on the issue.

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Enrolment drive
Updated 10 May, 2024

Enrolment drive

The authorities should implement targeted interventions to bring out-of-school children, especially girls, into the educational system.
Gwadar outrage
10 May, 2024

Gwadar outrage

JUST two days after the president, while on a visit to Balochistan, discussed the need for a political dialogue to...
Save the witness
10 May, 2024

Save the witness

THE old affliction of failed enforcement has rendered another law lifeless. Enacted over a decade ago, the Sindh...
May 9 fallout
Updated 09 May, 2024

May 9 fallout

It is important that this chapter be closed satisfactorily so that the nation can move forward.
A fresh approach?
09 May, 2024

A fresh approach?

SUCCESSIVE governments have tried to address the problems of Balochistan — particularly the province’s ...
Visa fraud
09 May, 2024

Visa fraud

THE FIA has a new task at hand: cracking down on fraudulent work visas. This was prompted by the discovery of a...