Low Graphics Site
White bar
.: Latest News :. .: News in Pictures :.
Dawn e-paper
Daily SectionMarker

Misc SectionMarker

Weekly SectionMarker

Weekly SectionMarker



Pakistan's Internet Magazine
Herald
Dawn GroupMarker

Archive, Search, Feedback & HelpMarker

Weather

FrontPage National International Local Business KSE Forex Sports Editorial Opinion Letters Features Today's Cartoon TV Guide Cowasjee Ayaz Irfan Hussain Jawed Naqvi Review Dawn Magazine Young World Images Dawn Group Subscription To Advertise

DINA
Previous Story DAWN - the Internet Edition Next Story

July 14, 2007 Saturday Jamadi-us-Sani 28, 1428





KARACHI: Reasons for delay in Lyari water project



By Our Staff Reporter


KARACHI, July 13: The Karachi Water and Sewerage Board (KWSB) has offered three reasons for the delay in the completion of the much-awaited Lyari water project. KWSB managing-director Ghulam Arif said on Friday that the Lyari town nazim had requested for an extension of the pipeline from Bakra Piri to Mira Naka besides a change of route from Lyari Nadi towards Mirza Adam Khan Road.

“These changes also resulted in an increase in the overall cost and delayed the project,” he stated.

A Lyari NGO had approached the Sindh High Court against a waterline project along the Lyari River. However, the court allowed the execution of the project as planned but the pace of work had suffered due to litigation, he added.

He said that another factor was the attitude of the previous contractor who was not serious about the project and was carrying out the work at a snail’s pace besides manoeuvring in a way to get the project’s cost raised. The contract was rescinded to save the financial interests of the water utility.