LAHORE, Oct 19: Contractors of the 24 dropped housing schemes initiated under the defunct Mera Ghar project have finally received a third of their dues from the Pakistan Housing Authority on account of work done before the schemes were shelved.

“I’m not sure about the exact amount outstanding on account of work done on the dropped schemes, but my guess is that it must be close to Rs20-30 million. The claims filed by the contractors for (financial) compensation on account of termination of the contracts are in addition to this amount,” Akbar Shaikh, a former chairman of the All Pakistan Contractors Association, told Dawn here on Friday.

The Mera Ghar project was launched by the previous government to provide low-cost housing to the people and 42 contracts were awarded under it before the military took over the government. Work was then suspended on all the schemes. Later, the military regime decided to go ahead with 18 schemes and discarded the remaining 24. When the PHA shelved the projects the contractors were promised that their bills would be cleared in a few weeks. However, added Mr Shaikh, “we have so far received only a third of the amount and there is no indication when the rest would be paid. Nor do we know when our claims for compensation would be decided.”

Mr Shaikh said most contractors were still willing to restart the dropped project “should the government allow them to do so on the developer’s model”. If their request was accepted, he said, it might generate economic activity and rejuvenate the Rs250 billion construction industry. “It would also generate tens of thousands of new jobs and help overcome shortage of housing in the country.”

Construction and related industries employ around 10 per cent of Pakistan’s work force and pay an average of 25 per cent tax.

Mr Shaikh said the country needed roughly 600,000 new units every year in view of its high population growth rate. He said only half the required number was were being built.

“This is adding to the country’s huge housing backlog of about six million units. Out of 300,000 units being constructed a year, 40 per cent are mud houses,” he said.

Opinion

Editorial

Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....
Soft on traders
08 Jun, 2026

Soft on traders

THE Fixed Tax Asaan Scheme for traders with an annual turnover of up to Rs200m has been designed as a ‘pragmatic...
Ceasefire in name
Updated 08 Jun, 2026

Ceasefire in name

Both sides accuse the other of violating the truce that was supposed to halt the conflict in April, yet neither appears willing to abandon negotiations altogether.
Damaged childhoods
08 Jun, 2026

Damaged childhoods

CHILD abuse is so prevalent that the UN ranked Pakistan as the least safe country for children. Even so, more than...