LAHORE: Construction work on the 108MW Golen Gol Hydropower Project has been expedited, while reliability of test run for Unit No 1 of the project dedicated to Chitral district is expected to be commissioned in October 2017.

This was told to Water and Power Development Authority (Wapda) Chairman Zafar Mahmood during his visit to the project site on Monday.

The chairman was also told that efforts were being made to complete the first unit by June 2017.

During the visit, the chairman had a detailed round of various sites of the project, including weir (dam), diversion tunnel, power house, switch yard and transmission line to review construction work.

On the occasion, the chairman said speedy completion of hydropower projects, including Golen Gol, was necessary to get rid of power shortages in the country and lowering the tariff for consumers.

He also mentioned that the prime minister had already instructed Wapda to provide 30 megawatts to Chitral district, as it needed electricity urgently after damage to the hydel facility in 2015 floods.

Expressing satisfaction over the project’s civil works, Mr Mahmood directed the authorities concerned to expedite electro-mechanical works as well. Similarly, he said, timely completion of the transmission line was also of equal importance, so that electricity generated by the project after its completion could be added to the national grid.

Earlier, general manager (projects), North, briefed the chairman about progress on the project. He also apprised him of the issues being faced, particularly the financial ones.

The project is being constructed on River Golen Gol, a tributary of River Mastuj. On completion, the project will contribute 442 million units of low-cost hydel electricity to the national grid annually.

Published in Dawn, May 31st, 2016

Opinion

Editorial

Iran stalemate
Updated 02 May, 2026

Iran stalemate

THE US and Iran are currently somewhere between war and peace. While a tenuous ceasefire — extended largely due to...
Tax shortfall
02 May, 2026

Tax shortfall

THE Rs684bn shortfall in tax collection during the first 10 months of the fiscal year is a continuation of a...
Teaching inclusion
02 May, 2026

Teaching inclusion

DISCRIMINATORY and exclusionary content in Punjab’s textbooks has been flagged in Inclusive Education for a United...
Water vision
01 May, 2026

Water vision

WATER insecurity in Pakistan has been building up for decades as per capita water availability has declined from...
Vaccine policy
01 May, 2026

Vaccine policy

PAKISTAN has finally approved its first National Vaccine Policy; a step the health ministry has rightly described as...
Labour rights
Updated 01 May, 2026

Labour rights

THE annual observance of May Day should move beyond statements about the state’s commitment to the rights of...