Rs11.3 per unit tariff approved for Nandipur project

Published April 16, 2015
Regulator puts on record that during the tenure of the previous federal government, the law and justice ministry was responsible for delaying the project for about four years during which period the project cost increased by about 160 per cent.  — AFP/file
Regulator puts on record that during the tenure of the previous federal government, the law and justice ministry was responsible for delaying the project for about four years during which period the project cost increased by about 160 per cent. — AFP/file

ISLAMABAD: The National Electric Power Regulatory Authority (Nepra) approved on Wednesday an average tariff, for 30 years, of Rs11.3 per unit for the 425MW Nandipur Power Project, expected to become operational by the end of next month.

In doing so, the regulator put on record that during the tenure of the previous federal government, the law and justice ministry was responsible for delaying the project for about four years during which period the project cost increased by about 160 per cent — from $329 million to $847m. In the process, the ministry caused a loss of over Rs113 billion to the nation until three years ago.

“The Ministry of Law, Justice and Parliamentary Affairs is responsible for causing a delay in completion of the documents. (Due to) the negligence on the part of executive authorities of the Ministry of Law, which has caused the delay, an approximate loss of more than Rs113bn has been caused to the National Exchequer up to April 2012,” the regulator said, quoting a report of judicial commission headed by a former judge of the Supreme Court, Rehmat Hussain Jafferi.

In its ruling, the Nepra also rejected an increase in project cost of Rs24bn, including Rs82m spent on the prime minister’s media campaign, saying the consumers did not cause any delay in project implementation and should not be penalised for follies of the government agencies.

The Nepra, however, kept open the option of including some expenses in the tariff at the time of commercial operation due next month, subject to documentary evidence. On provisional basis, the regulator adopted the overall project cost of Rs45bn instead of Rs69.5bn as sought by the Northern Power Generation Company (NPGC).

It held that cost overruns due to delays, the money spent on the prime minister’s media campaign and cost of the transmission line could not be transferred to consumers under the law which required recovery of only prudent costs from people.

The regulator also rejected the cost of a gas pipeline and gas-based power tariff for the project, saying that supply of gas to the project was a distant dream. The NPGC had sought a Rs18.17 per unit tariff for furnace oil-, Rs8.44 per unit for gas- and Rs28 per unit for high speed diesel-based power generation.

However, sources in the power ministry said the approved cost did not meet the commercial requirements of the project. They said the NPGC would be asked to submit a review petition to the regulator.

Published in Dawn, April 16th, 2015

On a mobile phone? Get the Dawn Mobile App: Apple Store | Google Play

Opinion

Editorial

Plugging the gap
06 May, 2024

Plugging the gap

IN Pakistan, bias begins at birth for the girl child as discriminatory norms, orthodox attitudes and poverty impede...
Terrains of dread
Updated 06 May, 2024

Terrains of dread

Restored faith in the police is unachievable without political commitment and interprovincial support.
Appointment rules
Updated 06 May, 2024

Appointment rules

If the judiciary had the power to self-regulate, it ought to have exercised it instead of involving the legislature.
Hasty transition
Updated 05 May, 2024

Hasty transition

Ostensibly, the aim is to exert greater control over social media and to gain more power to crack down on activists, dissidents and journalists.
One small step…
05 May, 2024

One small step…

THERE is some good news for the nation from the heavens above. On Friday, Pakistan managed to dispatch a lunar...
Not out of the woods
05 May, 2024

Not out of the woods

PAKISTAN’S economic vitals might be showing some signs of improvement, but the country is not yet out of danger....