Neelum project won’t be completed until late 2016, NA told

Published March 17, 2015
The government had earlier expected to make one of its units operational by the middle of the current year.—AFP/File
The government had earlier expected to make one of its units operational by the middle of the current year.—AFP/File

ISLAMABAD: The National Assembly was informed on Monday that the national grid would receive not a single watt of electricity from the 969MW Neelum-Jhelum hydropower project until late 2016.

The government had earlier expected to make one of its units operational by the middle of the current year.

However, in a written reply, Minister for Water and Power Khwaja Mohammad Asif assured the house that the government was working to increase power supply in the coming summer.

Also read: Neelum-Jhelum project may be further delayed, faces Rs50bn shortage

In response to a supplementary question, Minister of State for Water and Power Abid Sher Ali informed the assembly that the national grid would receive an additional 2,000MW by May this year.

But former minister for water and power Naveed Qamar of the PPP rejected the claim and said documents showed that the PML-N government had failed to add even a single unit to the national grid in two years of its rule.

The ministers failed to counter Mr Qamar’s claim with facts and started criticising the previous PPP government for not doing enough to improve the country’s power infrastructure.

The house was informed that PC-1 of the Neelum Jhelum project of 500MW had been approved in December 1989 to be completed by June 1998 at a cost of Rs15 billion. But work on the project could not be started because of non-availability of local and foreign financing and non-release of funds.

The first revised PC-1 for 969MW was approved in February 2002 for the project to be completed by 2007 at a cost of Rs84.502bn. But after the arrangement of financing, the project could only be started in January 2008 with completion date of October 2015.

As per amended schedule incorporated in the second revised PC-1, Ecnec approved the project in July 2013 to be completed by the end of 2016 at a cost of Rs274.882bn.

Published in Dawn March 17th , 2015

On a mobile phone? Get the Dawn Mobile App: Apple Store | Google Play

Opinion

Editorial

Punishing evaders
02 May, 2024

Punishing evaders

THE FBR’s decision to block mobile phone connections of more than half a million individuals who did not file...
Engaging Riyadh
Updated 02 May, 2024

Engaging Riyadh

It must be stressed that to pull in maximum foreign investment, a climate of domestic political stability is crucial.
Freedom to question
02 May, 2024

Freedom to question

WITH frequently suspended freedoms, increasing violence and few to speak out for the oppressed, it is unlikely that...
Wheat protests
Updated 01 May, 2024

Wheat protests

The government should withdraw from the wheat trade gradually, replacing the existing market support mechanism with an effective new one over the next several years.
Polio drive
01 May, 2024

Polio drive

THE year’s fourth polio drive has kicked off across Pakistan, with the aim to immunise more than 24m children ...
Workers’ struggle
Updated 01 May, 2024

Workers’ struggle

Yet the struggle to secure a living wage — and decent working conditions — for the toiling masses must continue.