Bhasha hydropower

Published September 21, 2014

IT has been reported (Sept 11) that state-run companies of Pakistan and China have finalised a programme under which the unit cost of electricity from the Kohala hydroelectric project for the first 12 years will be 8.9 cents per unit and 5.1 cents for the next 18 years.

This 1,100 MW project is to cost $2.4bn. This cost of $2.4bn is highly inflated. It should not be more than $1.2bn to $1.5bn.

Pakistan has a hydroelectric potential of over 60,000 MW identified and may well approach 100,000 MW. Over 87 projects are in various stages of development, starting with Wapda Vision 2025, based on 42 projects I had identified as the Planning Commission’s Energy Working Group in 1990-91.

I pursued these projects in over 60 articles in the press and at seminars and conferences. The Planning Commission’s Working Group on Hydropower and Alternative Energy, of which I was the chairman in 2010-2011, endorsed massive hydel development to be the main source of energy.

In 1975, at a conference on the role of hydroelectric resources in the development of Pakistan, my recommendations of building two major dams on the Indus after a ranking study were accepted.

The ranking study was delayed until 1981 because of the coup. It was completed in 1984 by Montreal Engineering. They ranked nine projects. Bhasha was ranked the best site technically and economically. Bhasha could have been completed in the early 1990s to give 4,500 MW of cheap hydropower and 8.1 maf of water storage, mitigating floods and increasing Tarbela’s life by 30 to 40 years.

Bhasha is being given and has to be given the highest priority if Pakistan is not to suffer a calamity. But it must be ensured that its cost is not inflated as Kohala’s.

Hydel is the only way we can have abundant and affordable electricity. If negotiated properly and honestly, per unit cost should be in the range of Rs2 to Rs3. Otherwise, if we persist with hydropower at these extremely high costs as Kohala’s, then our huge hydroelectric programme will be in jeopardy.

Without plentiful and affordable electricity, there can be no economic development, irrespective of how many motorways are built.

Imtiaz Ali Qazilbash

Islamabad

Published in Dawn, September 21th, 2014

Opinion

Editorial

Business concerns
Updated 26 Apr, 2024

Business concerns

There is no doubt that these issues are impeding a positive business clime, which is required to boost private investment and economic growth.
Musical chairs
26 Apr, 2024

Musical chairs

THE petitioners are quite helpless. Yet again, they are being expected to wait while the bench supposed to hear...
Global arms race
26 Apr, 2024

Global arms race

THE figure is staggering. According to the annual report of Sweden-based think tank Stockholm International Peace...
Digital growth
Updated 25 Apr, 2024

Digital growth

Democratising digital development will catalyse a rapid, if not immediate, improvement in human development indicators for the underserved segments of the Pakistani citizenry.
Nikah rights
25 Apr, 2024

Nikah rights

THE Supreme Court recently delivered a judgement championing the rights of women within a marriage. The ruling...
Campus crackdowns
25 Apr, 2024

Campus crackdowns

WHILE most Western governments have either been gladly facilitating Israel’s genocidal war in Gaza, or meekly...