ISLAMABAD, June 11: The government has allocated Rs76.2 billion for generating 2,200MW electricity to reduce loadshedding.

Tenders for the Diamer-Bhasha dam project will also be floated next year and the government expects work on the dam’s construction to start by mid-2009.

The power generation capacity is expected to be increased from 20,097MW now to 22,297MW in the next financial year with the addition of 2,200MW, says the Annual Plan 2008-09. This includes 1,297MW from rental plants and 615MW to be received from Independent Power Producers (IPPs). Nearly 205MW of Korangi Thermal Power Station and another 200MW coming from IPPs are expected to be added to the KESC system.

A total of 1500MW thermal power projects have been envisaged in Dadu, Guddu and Faisalabad in the next financial year.

The government has also planned generation of an aggregated 30MW in Northern Areas through Naltar-III and Naltar-V.

Opinion

Editorial

Centre vs provinces
Updated 10 Jun, 2026

Centre vs provinces

The reason the centre finds itself in this position is rooted in its failure to expand the tax net and boost revenues.
Party in crisis
10 Jun, 2026

Party in crisis

THE young KP chief minister must be starting to realise just how thorny a seat he occupies. There has been a flurry...
Varsity woes
10 Jun, 2026

Varsity woes

FINANCIAL crises affecting public sector universities across Pakistan are now having an impact on academic...
Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....