KARACHI, May 14: KESC MD Brig Tariq Saddozai has said that the completion of Hubco-KESC link in the next 18 months would help reduce the quantum of load-shedding by 40 per cent and another 30 per cent load-shedding would be eliminated after its project for construction of 12 new grid stations comes on the ground.

He was addressing a press conference, along with Nazim Naimatullah Khan, held to announce a relief package for payment of dues against inactive and active power consumers.

He said that these days the city was faced with a peak power demand for 2059 MW as against 1500 MW being generated by KESC.

He pointed out that 550 MW are provided by Wapda through its two Jamshoro circuits. He said in case a circuit trips, the KESC is deprived of a supply of 250 MW. He said the loadshedding in Karachi experienced recently was because both circuits tripped and KESC had to depend on its own generated power.-APP

Opinion

Editorial

GB polls’ aftermath
Updated 11 Jun, 2026

GB polls’ aftermath

The new administration must address the region’s issues proactively.
Peace in retreat
11 Jun, 2026

Peace in retreat

THE ceasefire announced in April was supposed to create space for negotiations. Instead, it has been repeatedly...
A few good men
11 Jun, 2026

A few good men

IT was a brave move, no doubt. This Tuesday, in the land of the Afghan Taliban, a few good men decided to take a...
Centre vs provinces
Updated 10 Jun, 2026

Centre vs provinces

The reason the centre finds itself in this position is rooted in its failure to expand the tax net and boost revenues.
Party in crisis
10 Jun, 2026

Party in crisis

THE young KP chief minister must be starting to realise just how thorny a seat he occupies. There has been a flurry...
Varsity woes
10 Jun, 2026

Varsity woes

FINANCIAL crises affecting public sector universities across Pakistan are now having an impact on academic...