LAHORE, July 19: The Italian contractors of the Ghazi Barotha Hydel Project have been paid $45 million — $25 million as security and $20 million advance payment — for restarting their work after their Sept 11 interruption, GBHP chief resident engineer Abdul Khalaq Khan and the Pakistan Hydro Power chief executive Amjad Agha told a team of visiting journalists.

The Water and Power Development Authority had arranged the tour to the project site.

Engr Agha said both amounts would be recovered before completion of the project. He said the GBHP was 95 per cent complete. Its first unit would start operating by the middle of next year.

With an installed capacity of 1,450 MW, he said, the GBHP would work daily during the four hour power load peak. This will include the power deficient months of May and June. The first unit was scheduled to come online in June 2002. The project was delayed, however, when the Italian contractor discontinued work after Sept 11. Engr Agha said the work was in full swing. He hoped that the revised schedule would be met.

He said the project had three main components; a barrage situated at Ghazi village (a place near Tarbela), a 52-kilometre long power channel from Ghazi to Barotha, and a power complex.

He said resettlement of the displaced population had been completed and everybody affected by the project had been paid compensation. He said only 110 dwellings had been relocated to three resettlement villages near Isa, Feroze Banda and Barotha.

He said land was acquired at the market rate estimated by a land evaluation committee comprising representatives of those affected, the Wapda and non-government organizations.

About 200 people, including Japanese, British, American, Chinese and German nationals, were currently working for it.

Earlier, Brig Muhammad Zarreen showed the project site to the journalists from Kamra to Barotha.

Opinion

Editorial

Centre vs provinces
Updated 10 Jun, 2026

Centre vs provinces

The reason the centre finds itself in this position is rooted in its failure to expand the tax net and boost revenues.
Party in crisis
10 Jun, 2026

Party in crisis

THE young KP chief minister must be starting to realise just how thorny a seat he occupies. There has been a flurry...
Varsity woes
10 Jun, 2026

Varsity woes

FINANCIAL crises affecting public sector universities across Pakistan are now having an impact on academic...
Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....