PESHAWAR: Power shutdown notice

Published July 17, 2007

PESHAWAR, July 16: Power supply will remain suspended from the 132KV grid station in Peshawar Fort on July 17 and 19 from 6am to 11am due to necessary repair work. The consumers of the 11KV Fort feeder would have to do without power, as a result.

Similarly, electricity supply will remain suspended from the 132KV grid station in Peshawar Cantonment on July 17 and 19. The consumers of the 11KV MES feeder would face an outage.

From the 132KV grid station in Cantt, supply would remain suspended on July 19 from 6am to 11am due to which consumers of the 11KV Palosy feeder will face inconvenience.

SUPPLY RESTORED: Power supply has been restored from the 132KV grid station in the Ghallanai Mohmand Agency, which was disrupted due to the collapse of three pylons near Saro Kaley in November.—APP