How World Bank arbitrators mugged Pakistan

Published November 27, 2019
The World Bank Group headquarters building in Washington.
The World Bank Group headquarters building in Washington.

NEW YORK: Wall Street hedge funds and lawyers have turned an arcane procedure of international treaties into a money machine, at the cost of the world’s poorest people. The latest shakedown is a $5.9 billion award against Pakistan’s government in favour of two global mining companies — Antofagasta PLC of Chile and Barrick Gold Corporation of Canada — for a project that was never approved by Pakistan and never carried out.

Here are the facts:

In 1993, a US-incorporated mining company, BHP, entered into a joint venture (JV) with the Balochistan Development Authority (BDA), a public corporation in Pakistan’s impoverished Balochis­tan province. The JV was set up to prospect for gold and copper, and in the event of favourable discoveries, to seek a mining license. BHP was not optimistic about the project’s profitability and dragged its feet on exploration. In the early 2000s, it assigned the prospecting rights to an Australian company, which created Tethyan Copper Company (TCC) for the project.

In 2006, Antofagasta acquired TCC for $167 million, and sold half to Barrick Gold. Soon after the purchase, however, the original JV agreement with BHP was challenged in Pakistan’s courts. In 2013, the Pakistan Supreme Court found that the JV’s terms violated Pakistan’s mining and contract laws in several ways and declared the agreement — and thus the rights claimed by TCC — to be null and void.

Specifically, the Court ruled that the BDA did not have authority to bind Balochistan to the terms of the JV agreement; that it awarded the contract without competition or transparency; and that it had greatly exceeded its authority and violated the law by promising extensive deviations from the rules normally applicable to mining projects. Moreover, the JV failed to obtain, and even to pursue, many mandatory approvals from the state and federal governments, and BHP failed to undertake prospecting in a timely manner required under the mining law.

The Supreme Court’s decision came after years of public-interest litigation challenging the deal for violations of domestic law and the rights of the public. In the meantime, the BDA’s chairman was found to have conflicts of interest and to be living beyond the means afforded by his official salary, which in the Court’s words was tantamount to corruption.

In a normal world, the Court’s judgment would be respected absent proven evidence of corruption or other wrongdoing against the justices. But in the world we actually inhabit, the so-called international rule of law enables rich companies to exploit poor countries with impunity and disregard their laws and courts.

When TCC lost its case in Pakistan’s Supreme Court, it simply turned to the World Bank’s International Center for the Settlement of Investment Disputes (ICSID), in complete disregard of Pakistan’s laws and institutions. A panel of three arbitrators with no expertise in or respect for Pakistan’s legal system ruled that TCC deserved compensation for all future profits that it allegedly would have earned if the non-existent project, based on a voided agreement, had gone forward!

Because there was no actual project, and no agreement for one, the arbitrators had no basis to say what terms — royalties, corporate taxes, environmental standards, land area, and other basic provisions — the governments of Balochistan and Pakistan would have set. In fact, disagreement on many of those terms had stalled negotiations for years.

Nonetheless, the ICSID panel arbitrarily decided that TCC would have had the right to mine 1,000 square kilometres, though the mining law forbade licensing such a vast area. The arbitrators ruled that TCC would have received a tax holiday for 15 years, even though there is no evidence that such a tax holiday was in the offing — or even legal. The arbitrators decided that TCC would have benefited from a royalty rate several percentage points below the mandatory statutory rate, though there is no reason why Pakistan would have set such a low rate.

The arbitrators also ruled that TCC would have met all environmental standards, or that the government would have exempted TCC from relevant requirements, though the mining area is in a desert region subject to extreme water stress, and the mining project would have demanded vast amounts of water. And the arbitrators ruled that to obtain the land needed for TCC’s pipeline, the government would have taken it from its owners and inhabitants.

The arbitration ruling is utterly capricious. An illegal project, declared null and void by Pakistan’s Supreme Court and never pursued, was found by the World Bank’s arbitration panel to be worth more than $4 billion to TCC’s owners, who had paid $167m for it in 2006. Moreover, the tribunal declared that Pakistan must compensate TCC in full, with back interest, and cover its legal fees, raising the bill to $5.9bn, or roughly 2 per cent of Pakistan’s GDP. It is more than twice Pakistan’s entire public spending on health care for 200m people, in a country where 7pc of children die before their fifth birthday. For many Pakistanis, the World Bank’s arbitration ruling is a death sentence.

The ICSID is not an honest broker. One of the tribunal members in the TCC case is using the same expert put forward by TCC for another case in which the arbitrator is acting as counsel! When challenged about this obvious conflict of interest, the arbitrator refused to step down and the ICSID proceeded as if all were normal.

Thanks to the World Bank’s arbitrators, the rich are making a fortune at the expense of poor countries. Multinational companies are feasting on unapproved, non-existent projects. Fixing the broken arbitration system should start with a reversal of the outrageous ruling against Pakistan and a thorough investigation of the flawed and corrupt process that made it possible.

Written by Columbia University Professor Jeffrey D Sachs for Project Syndicate

Published in Dawn, November 27th, 2019

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Large projects again?
Updated 03 Jun, 2024

Large projects again?

Government must focus on debt sustainability by curtailing its spending and mobilising more resources.
Local power
03 Jun, 2024

Local power

A SIGNIFICANT policy paper was recently debated at an HRCP gathering, calling for the constitutional protection of...
Child-friendly courts
03 Jun, 2024

Child-friendly courts

IN a country where the child rights debate has been a belated one, it is heartening to note that a recent Supreme...
Dutch courage
Updated 02 Jun, 2024

Dutch courage

ECP has been supported wholeheartedly in implementing twisted interpretations of democratic process by some willing collaborators in the legislature.
New World cricket
02 Jun, 2024

New World cricket

HAVING finished as semi-finalists and runners-up in the last two editions of the T20 World Cup in familiar ...
Dead on arrival?
02 Jun, 2024

Dead on arrival?

Whatever the motivations for Gaza peace plan, it is difficult to see the scheme succeeding.