LAHORE: The Pakistan Water and Power Development Authority (Wapda) has decided to submit PC-I of the implementation of the 1410-M Tarbela, fifth extension hydropower project.

The PC-1 of the $795.8 million project will be submitted to the Ministry of Water and Power for approval of the Planning Commission.

This decision was made in a meeting of the authority held here on Friday at Wapda House. The meeting, presided over by Wapda Chairman Zafar Mahmood, was attended by Member (water) Muhammad Shoaib Iqbal, Member (power) Badrul Munir Murtiza, Member (finance) Anwarul Haq and Wapda Secretary Syed Khalid Akhlaq Gilani.

The project authorities and representatives of the consultants were also present on the occasion.

A presentation was made on the PC-I of the project in the meeting by General Manager (Tarbela Dam project) Iqbal Maqsood Siddiqui who discussed the estimates quoted in the PC-I.

Participants noted the revision of PC-I of the projects resulted in escalation of the cost, and delayed their scheduled completion.

The Tarbela 5th Extension Hydropower Project is part of the least-cost hydel power generation plan of the federal government, being executed by Wapda on priority. The project is like a low-hanging fruit, benefits of which may be accrued in a very short span of time as the project will be completed before the high-flows season of 2018.

Under the project, the existing Tunnel No 5 of the Tarbela Dam will be converted into power tunnel without affecting the irrigation release capabilities. As many as three units with generation capacity of 470MW each will be installed to generate 1,410MW electricity during the summer season. It is a low-risk and high-reward project aimed at providing more than 1.8 billion units of the lost-cost hydel electricity to the national grid per annum. The project’s financial internal rate of return has been estimated at 13.5 per cent.

The installed capacity of the existing 3,478MW-Tarbela Hydel Power Station will rise to 4,888MW after the completion of the under-construction Tarbela 4th extension and 6,298MW after the completion of the fifth project.

Published in Dawn, March 28th, 2015

On a mobile phone? Get the Dawn Mobile App: Apple Store | Google Play

Opinion

Editorial

Impending slaughter
Updated 07 May, 2024

Impending slaughter

Seven months into the slaughter, there are no signs of hope.
Wheat investigation
07 May, 2024

Wheat investigation

THE Shehbaz Sharif government is in a sort of Catch-22 situation regarding the alleged wheat import scandal. It is...
Naila’s feat
07 May, 2024

Naila’s feat

IN an inspirational message from the base camp of Nepal’s Mount Makalu, Pakistani mountaineer Naila Kiani stressed...
Plugging the gap
06 May, 2024

Plugging the gap

IN Pakistan, bias begins at birth for the girl child as discriminatory norms, orthodox attitudes and poverty impede...
Terrains of dread
Updated 06 May, 2024

Terrains of dread

Restored faith in the police is unachievable without political commitment and interprovincial support.
Appointment rules
Updated 06 May, 2024

Appointment rules

If the judiciary had the power to self-regulate, it ought to have exercised it instead of involving the legislature.