Financial crisis hits PFF

Published July 20, 2004

LAHORE, July 19: Pakistan Football Federation (PFF) faces a shortfall of $250,000 for completing FIFA-funded Goal Project in Lahore because of lack of planning.

FIFA, the world governing body of the game, had allocated $400,000 in 2001 for the Project to the national federations including Pakistan. But the previous PFF could not start the work on the project due to lack of interest.

Finally present officials elected last year secured a piece of land for the project and held foundation laying ceremony last December. PFF had vowed to launch the project in the first week of July. The process of awarding the contract is still in progress which could prolong owing to budget deficit.

PFF called tenders, according to which the minimum bid for the project was around $620,000, while the maximum was $700,000. Besides, PFF has to pay $35,000 to the consultant of the project.

However, PFF cancelled the first design of the project which was approved by FIFA during the tenure of former PFF president Mian Azhar. The present official cancelled the design to expand the construction area of the project.

It not only took another six months to get FIFA's approval for the new design, the new plan also raised the cost of the project. PFF is now considering three options to cover up the deficit.

Top priority is being given to get sponsors which seems difficult as the federation has even failed to seek sponsorship for the ongoing national league. The second option is to use FIFA's annual grant of $250,000.

Although PFF has some amount, the federation has been meeting expenditures of the league and the staff, therefore, it will be hard to support the Goal through the annual FIFA aid. The third option is to reduce the activities till the completion of the Goal Project or to get sponsorships for domestic activity.

Opinion

Editorial

Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....
Soft on traders
08 Jun, 2026

Soft on traders

THE Fixed Tax Asaan Scheme for traders with an annual turnover of up to Rs200m has been designed as a ‘pragmatic...
Ceasefire in name
Updated 08 Jun, 2026

Ceasefire in name

Both sides accuse the other of violating the truce that was supposed to halt the conflict in April, yet neither appears willing to abandon negotiations altogether.
Damaged childhoods
08 Jun, 2026

Damaged childhoods

CHILD abuse is so prevalent that the UN ranked Pakistan as the least safe country for children. Even so, more than...