KOHAT, Feb 9: The National Highway Authority has asked the Japanese construction firm, Taisei, working on the Rs seven billion Kohat Tunnel project, to replace the emergency systems proposed in the old plan of the project with the latest gadget for the safety of passengers inside the 1.889-kilometre-long tunnel, Dawn learnt here on Saturday.

The NHA plans to send its staff to Japan for training to operate fire fighting equipment, standby generators, supply of water,  emergency repair of vehicles and other  electrical facilities proposed in the project.

Earlier, the tunnel plan had the provision for only fire extinguishers, which were to be used by the drivers in case of emergency. Now there will be a separate staff for dealing with emergency situation inside the tunnel.

The project director, Engineer Pervez Gul, talking to Dawn said that the excavation of the whole tunnel would be completed by the end of March as directed by the NWFP Governor Syed Iftikhar Hussain Shah to make up for the delay caused due to the absence of the foreign consultants during the US bombardment of Afghanistan.

He said that the installation of equipment, renovation of interior and construction of link roads would take extra one year and the tunnel would be ready for public use by April 2003.

Opinion

Editorial

Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....
Soft on traders
08 Jun, 2026

Soft on traders

THE Fixed Tax Asaan Scheme for traders with an annual turnover of up to Rs200m has been designed as a ‘pragmatic...
Ceasefire in name
Updated 08 Jun, 2026

Ceasefire in name

Both sides accuse the other of violating the truce that was supposed to halt the conflict in April, yet neither appears willing to abandon negotiations altogether.
Damaged childhoods
08 Jun, 2026

Damaged childhoods

CHILD abuse is so prevalent that the UN ranked Pakistan as the least safe country for children. Even so, more than...