LAHORE, Feb 8: The Water and Power Development Authority has warned the Italian contractors of the Ghazi Brotha Hydro-electric Power Project to either return by mid-February or face legal action for skirting its contractual obligations, Dawn learnt here on Friday.

The Italian contractor company, Impregilo, had left the project in October last without any authorisation from the engineer. The act of the firm is costing the government of Pakistan around one million dollars per day and the total loss has already touched the figure of $100 million.

Now the Wapda authorities are in the process of forming a Task Force to bypass procedural hiccups in case Impregilo fails to return by Feb 14. The authority feels the rest of the work could still be completed in time if all available alternative local resources are mobilised without any further delay. The Task Force can quickly take decision and sublet parts of the project in order to speed up the work.

The Wapda authorities have already evaluated the leftover work of the project and work on detailed drawings resumed. The Pakistani partners of the Impregilo have also reportedly asked the Italian firm to return to work and save them huge financial loss that Wapda’s legal action could cost them.

The lending agencies have also reportedly told the Italians to return because there was no security problem at present.

The government of Pakistan and Wapda authorities had maintained that the European governments had declared the NWFP and Balochistan security risk zones. But the Ghazi Brotha project is situated in Punjab that never fell in security risk bracket. The Italians, already looking for excuses to leave, took refuge behind the clause and ran away.

Opinion

Editorial

Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....
Soft on traders
08 Jun, 2026

Soft on traders

THE Fixed Tax Asaan Scheme for traders with an annual turnover of up to Rs200m has been designed as a ‘pragmatic...
Ceasefire in name
Updated 08 Jun, 2026

Ceasefire in name

Both sides accuse the other of violating the truce that was supposed to halt the conflict in April, yet neither appears willing to abandon negotiations altogether.
Damaged childhoods
08 Jun, 2026

Damaged childhoods

CHILD abuse is so prevalent that the UN ranked Pakistan as the least safe country for children. Even so, more than...