WB ready to fund Bhasha dam

Published January 19, 2006

ISLAMABAD, Jan 18: The World Bank on Wednesday indicated its readiness to finance Bhasha and other viable dams but called for implementation of water accord and replacement of prevailing royalty payment patterns to provinces.

Speaking at a news conference, country representative of the World Bank John W. Wall, however, said the geological and technical studies of the Bhasha dam were not available and the bank had not yet analyzed its economic rate of return. However, he said, it was presumed that it would be a good investment.

He also formally released a report “Pakistan: Country Water Resource Assistance Strategy, Water Economy: Running Dry”, which has extensively been published in the press a couple of months ago. The bank will conduct the appraisal of the project, examine its economic rate of return and ensure that environmental and displacement concerns were mitigated.

He termed Bhasha dam’s cost estimate at $6.5 billion very old and said it was based on calculations made before the completion of its feasibility study. Similarly, he said the cost estimate of Kalabagh dam at $6 billion was also very old.

In his opinion, Pakistan will have to announce a National Settlement Policy for the resettlement and compensation for people to be displaced by the construction of new dams to qualify for the World Bank financing.

He said major investments in irrigation would remain a major challenge because of fiscal responsibility law that puts a maximum on the amount of public debt the government could borrow.

He said the economy was booming but the government’s abilities to mobilize tax revenue to pay for public goods remained low and there were many priorities for development in addition to water sector.

He said Pakistan needed to appoint a neutral water auditor.

Opinion

Editorial

Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....
Soft on traders
08 Jun, 2026

Soft on traders

THE Fixed Tax Asaan Scheme for traders with an annual turnover of up to Rs200m has been designed as a ‘pragmatic...
Ceasefire in name
Updated 08 Jun, 2026

Ceasefire in name

Both sides accuse the other of violating the truce that was supposed to halt the conflict in April, yet neither appears willing to abandon negotiations altogether.
Damaged childhoods
08 Jun, 2026

Damaged childhoods

CHILD abuse is so prevalent that the UN ranked Pakistan as the least safe country for children. Even so, more than...