Work on 32km Darra-Peshawar gas pipeline nears completion

Published January 22, 2019
SNGPL General Manager Arbab Mohammad Saqib being briefed about the gas pipeline project in Peshawar on Sunday. — Dawn
SNGPL General Manager Arbab Mohammad Saqib being briefed about the gas pipeline project in Peshawar on Sunday. — Dawn

PESHAWAR: Work on 32km gas supply line from Darra Adamkhel to Peshawar is nearing completion to augment and address low gas pressure issue of tail-end consumers in nearly half the provincial metropolis, it was learnt here on Monday.

Engineers working at the sales meter station Peshawar, while briefing SNGPL General Manager Arbab Mohammad Saqib disclosed that work on the 16-inch diameter pipeline directly linking gas field in the southern districts of KP with Peshawar would be ready by early next week, much ahead of its scheduled date of completion.

The project, costing Rs560 million, was originally scheduled to be completed by June 2019.

The pipeline traverses some of the most difficult and risky terrains including areas once seen as badly affected by militancy to reach all the way from the arms manufacturing market to Peshawar.

The new pipeline would augment gas pressure in areas like University Town, Hayatabad, Regi Model Town and could be further extended beyond to provide gas to consumers as far as in the tribal districts of Khyber, Mr Saqib was told.

Similarly, a 16-inch diameter pipeline spanning over 8.1 kms costing Rs160 million would provide direct gas to the industrial estate near Hayatabad and enhance the already existing gas system.

Mr Saqib said that plans were afoot to separate CNG stations from domestic consumers’ supply line.

Besides, the upgradation of 27km pipeline along the under-construction BRT route had already been commissioned.

The SNGPL GM, while speaking on the occasion said that old pipeline system laid down in the 1970s and 1980s had already been upgraded at a cost of Rs253 million.

He added that 90 per cent of work on the pipeline had already been completed costing Rs300 million through which major lacunas in the gas supply system would be addressed.

“Our workers and engineers are working day and night to complete the projects on war footing, he said.

Published in Dawn, January 22nd, 2019

Opinion

Editorial

X post facto
Updated 19 Apr, 2024

X post facto

Our decision-makers should realise the harm they are causing.
Insufficient inquiry
19 Apr, 2024

Insufficient inquiry

UNLESS the state is honest about the mistakes its functionaries have made, we will be doomed to repeat our follies....
Melting glaciers
19 Apr, 2024

Melting glaciers

AFTER several rain-related deaths in KP in recent days, the Provincial Disaster Management Authority has sprung into...
IMF’s projections
Updated 18 Apr, 2024

IMF’s projections

The problems are well-known and the country is aware of what is needed to stabilise the economy; the challenge is follow-through and implementation.
Hepatitis crisis
18 Apr, 2024

Hepatitis crisis

THE sheer scale of the crisis is staggering. A new WHO report flags Pakistan as the country with the highest number...
Never-ending suffering
18 Apr, 2024

Never-ending suffering

OVER the weekend, the world witnessed an intense spectacle when Iran launched its drone-and-missile barrage against...