PESHAWAR: The Peshawar Electric Supply Company has announced that power supply will remain suspended from various grid stations in the provincial capital on Thursday (today) and Friday from 9am to 12pm due to maintenance work on the transmission lines.
According to a statement issued here on Wednesday, power supply will remain suspended from 132KV industrial grid station, troubling consumers of 11KV Sonehri Masjid, Gulberg, Nothia, Swati Gate, Bana Mari, Amin Colony and New Kohat Road feeder.
Similarly, power supply will remain suspended from 132KV Peshawar Cantonment grid station, resultantly consumers of 11KV University Town, Islamia College and Tehkal feeder would be affected.
Power supply suspension from Danishabad grid station will hit consumers of 11KV Circular Road, Danish Abad, Engineering, Canal Town, University Campus, Agriculture, Jamaluddin and Malakander feeder.
Published in Dawn, June 21st, 2018