Russia’s World Cup stadium in Samara behind schedule

Published August 24, 2017
SAMARA: A worker moves equipment during the construction work at the Samara Arena Stadium on Wednesday.—AFP
SAMARA: A worker moves equipment during the construction work at the Samara Arena Stadium on Wednesday.—AFP

SAMARA: Construction work on the World Cup stadium in the Russian city of Samara is about 30 days behind schedule, the company building the venue said on Wednesday, adding it would make up the lost time.

Work on the new 45,000-seat stadium, one of 12 that will host World Cup matches next summer, has been plagued by delays over the past months.

“We would have liked a faster construction pace,” Sergei Ponomaryov, the deputy head of general contractor PSO Kazan, told reporters. “We have calculated that we are behind by about 30 days.”

Ponomaryov said all major construction work at the venue would be finished by the end of the year, the initial deadline for its completion.

But on Wednesday cranes dominated the skyline above the venue and towering metal structures were supporting its roof.

The pitch also not been laid, unlike at some other venues being built for the tournament.

The governor of the Samara region, Nikolai Merkushkin, blamed the delay on unfavourable weather, including heavy rain in the Spring.

“In September we will be back on track,” he said.

Deputy Prime Minister Vitaly Mutko said last month there was “no doubt” the venue would be ready by the end of the year, TASS news agency reported.

The Samara Arena will host four group stage matches, a match in the round-of-16 and a quarter final.

Published in Dawn, August 24th, 2017

Opinion

Editorial

By-election trends
Updated 23 Apr, 2024

By-election trends

Unless the culture of violence and rigging is rooted out, the credibility of the electoral process in Pakistan will continue to remain under a cloud.
Privatising PIA
23 Apr, 2024

Privatising PIA

FINANCE Minister Muhammad Aurangzeb’s reaffirmation that the process of disinvestment of the loss-making national...
Suffering in captivity
23 Apr, 2024

Suffering in captivity

YET another animal — a lioness — is critically ill at the Karachi Zoo. The feline, emaciated and barely able to...
Not without reform
Updated 22 Apr, 2024

Not without reform

The problem with us is that our ruling elite is still trying to find a way around the tough reforms that will hit their privileges.
Raisi’s visit
22 Apr, 2024

Raisi’s visit

IRANIAN President Ebrahim Raisi, who begins his three-day trip to Pakistan today, will be visiting the country ...
Janus-faced
22 Apr, 2024

Janus-faced

THE US has done it again. While officially insisting it is committed to a peaceful resolution to the...