Indonesia calls for solar power project investment

Published November 6, 2013
- File Photo
- File Photo

JAKARTA: The government is tendering as many as 80 projects related to the development of solar power plants in an attempt to boost the country’s renewable energy supplies.

The 80 projects will have a combined capacity of up to 140 megawatts (MW), according to Energy and Mineral Resources Ministry director general for renewable energy Rida Mulyana.

The ministry opened the tender starting last Thursday and is expected to announce the winners of the projects by this December.

“The solar plants’ construction will take about six months. Therefore, we will see the plants commence operation in the middle of next year,” Rida said as quoted by Antara news agency.

He added most of the solar power plants would be located in eastern Indonesia, such as in Papua, West Papua, Maluku, Sulawesi and Nusa Tenggara. Most of the power plants will have a 1 MW capacity while the biggest project will be located in Jayapura, Papua, with a 6 MW capacity.

According to Rida, at least nine units of power plants would be offered for development in East Nusa Tenggara (NTT) with a total capacity of 14 MW. He said seven locations in Papua would host solar power plants with a 14.5 MW capacity, six locations in North Maluku with a combined capacity of 7.5 MW, six developments in Maluku with 9.5 MW and another six projects in North Sulawesi with 13 MW.

There will also be three locations in Aceh hosting 4 MW solar power plants, six units in Riau with an 8.5 MW capacity, seven units in West Kalimantan with a 9.5 MW capacity, five unit plants in West Nusa Tenggara (NTB) with 17 MW and four units in East Java with a 4 MW capacity.

The 140 MW projects will need roughly 2.8 trillion rupiah in investment. Earlier this year, the government inaugurated the largest capacity solar power plant in Karangasem, Bali. The plant has a 1 MW capacity and cost 26 billion rupiah in investment.

The government has put aside 400 billion rupiah on the development of solar power plants this year.

According to the announcement on the renewable energy directorate’s website, the tenders of power plant projects have been open for development in Kupang, NTT and in North Lombok, NTB, with 5 MW and 2 MW capacities, respectively.

Despite abundant potential in renewable energy, the country remains heavily dependent on the fossil fuel for its electricity supply.

According to a report in the renewable energy directorate general, the country’s solar power plants’ installed capacity had reached 59 MW as of early November.

Energy and Mineral Resources Minister Jero Wacik said the country had a solar energy potential of 50,000 MW. “A number of companies came to us and said they wanted to build plants,” Jero said at an event recently.

Attempting to boost solar power plant development, the Energy and Mineral Resources Ministry issued last June Ministerial Decree no. 17 2013, which regulates the purchasing of electricity produced by photovoltaic solar power plants by state-owned electricity company PT Perusahaan Listrik Negara (PLN).

– By arrangement with the ANN/The Jakarta Post –

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Ties with Tehran
Updated 24 Apr, 2024

Ties with Tehran

Tomorrow, if ties between Washington and Beijing nosedive, and the US asks Pakistan to reconsider CPEC, will we comply?
Working together
24 Apr, 2024

Working together

PAKISTAN’S democracy seems adrift, and no one understands this better than our politicians. The system has gone...
Farmers’ anxiety
24 Apr, 2024

Farmers’ anxiety

WHEAT prices in Punjab have plummeted far below the minimum support price owing to a bumper harvest, reckless...
By-election trends
Updated 23 Apr, 2024

By-election trends

Unless the culture of violence and rigging is rooted out, the credibility of the electoral process in Pakistan will continue to remain under a cloud.
Privatising PIA
23 Apr, 2024

Privatising PIA

FINANCE Minister Muhammad Aurangzeb’s reaffirmation that the process of disinvestment of the loss-making national...
Suffering in captivity
23 Apr, 2024

Suffering in captivity

YET another animal — a lioness — is critically ill at the Karachi Zoo. The feline, emaciated and barely able to...