ISLAMABAD, Oct 30: The Civil Aviation Authority (CAA) on Tuesday said it was acquiring another 4,000 kanals of land at the site of the under-construction New Islamabad International Airport (NIIA) to build a second runway.

The original plan had a main and an emergency runway, however, it dawned upon the CAA management at a much later stage that they needed to build another runway to make the airport compatible with international standards.

Briefing mediapersons about the progress of the project, CAA Director Planning and Development Vikram Soda said that the process of land acquisition had been initiated through the Punjab government.

The cost of land was fixed at about Rs0.56 million per kanal. Owners would be getting additional amount for any construction on their land, he added.

The new airport is being built in Pind Ranja near Fatehjang. Some 3,500 acres of land had already been acquired for the project expected to cost Rs35 billion.

The earlier land acquisition process that continued for about a couple of decades was marred by allegations of corruption and favouritism. It had been alleged that CAA had violated the Land Acquisition Act, 1894, while acquiring some additional chunks of land during the first phase.

The runways being constructed at the airport, Mr Soda said, would be of Category E — capable of handling even the most modern aircraft like the recently launched A-380.

The CAA official claimed that the site preparation work was on course and 54 per cent of it had been completed since the project took off in April this year. He hoped that the contractors would be able to complete the site preparation ahead of their scheduled completion date of February 2008.

About the progress on design preparations for what is being billed as the most modern and state-of-the-art airport in the region, Mr Doda said that preliminary design had been prepared, which would be finalised in three months.

CAA has decided to divide the construction contract into two packages.

The contract for the first package comprising airside works would be awarded in January next with a completion time of 24 months. The second package contract, which included construction of terminal building and the ancillary structures, would be awarded in February 2008, which would take 30 months to complete.

Brushing aside concerns about the financial viability of the project, CAA Director-General Farooq Rehmatullah said that the payback period for the new airport project is estimated to be 10- 12 years, which is good according to the industry standards.

Opinion

Editorial

X post facto
19 Apr, 2024

X post facto

AS has become its modus operandi, the state is using smoke and mirrors to try to justify its decision to ban X,...
Insufficient inquiry
19 Apr, 2024

Insufficient inquiry

UNLESS the state is honest about the mistakes its functionaries have made, we will be doomed to repeat our follies....
Melting glaciers
19 Apr, 2024

Melting glaciers

AFTER several rain-related deaths in KP in recent days, the Provincial Disaster Management Authority has sprung into...
IMF’s projections
Updated 18 Apr, 2024

IMF’s projections

The problems are well-known and the country is aware of what is needed to stabilise the economy; the challenge is follow-through and implementation.
Hepatitis crisis
18 Apr, 2024

Hepatitis crisis

THE sheer scale of the crisis is staggering. A new WHO report flags Pakistan as the country with the highest number...
Never-ending suffering
18 Apr, 2024

Never-ending suffering

OVER the weekend, the world witnessed an intense spectacle when Iran launched its drone-and-missile barrage against...