LAHORE: Following improved hydrological conditions and availability of water, the first unit of Tarbela 4th Extension Hydropower Project has started electricity generation.

The unit, which is passing through its reliability run test these days, has been providing 335MW of electricity to the national grid, which will be gradually increased to its maximum capacity of 470MW.

“Though first unit was completed in April, it could not start electricity generation owing to non-availability of water caused by low inflows in River Indus at Tarbela in current year,” said a spokesman for the Pakistan Water and Power Development Authority (Wapda).

The second unit of Tarbela 4th Extension Hydropower Project has also been put into wet commissioning three days ago. This unit is scheduled to enter its reliability run test phase in next month’s first week, he added.

The 1,410MW Tarbela 4th Extension Project having three electric power generating units — each of them 470MW capacity — has been built at the Tunnel 4 of Tarbela Dam. The project is a component of least-cost energy generation plan being implemented by Wapda on priority to meet electricity requirements in the country and increase the ratio of hydro electricity in the National Grid to stabilise electricity tariff for the consumers.

With completion of the project, generation capacity of the existing Tarbela Hydel Power Station will increase to 4,888MW from the existing 3,478MW. The project will provide 3.84 billion units of electricity to the national grid per annum. “Annual benefits of the project have been estimated at Rs30bn. It will pay back its cost in just three years,” the spokesman said.

Published in Dawn, June 12th, 2018

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Tough talks
Updated 16 Apr, 2024

Tough talks

The key to unlocking fresh IMF funds lies in convincing the lender that Pakistan is now ready to undertake real reforms.
Caught unawares
Updated 16 Apr, 2024

Caught unawares

The government must prioritise the upgrading of infrastructure to withstand extreme weather.
Going off track
16 Apr, 2024

Going off track

LIKE many other state-owned enterprises in the country, Pakistan Railways is unable to deliver, while haemorrhaging...
Iran’s counterstrike
Updated 15 Apr, 2024

Iran’s counterstrike

Israel, by attacking Iran’s diplomatic facilities and violating Syrian airspace, is largely responsible for this dangerous situation.
Opposition alliance
15 Apr, 2024

Opposition alliance

AFTER the customary Ramazan interlude, political activity has resumed as usual. A ‘grand’ opposition alliance ...
On the margins
15 Apr, 2024

On the margins

IT appears that we are bent upon taking the majoritarian path. Thus, the promise of respect and equality for the...