KARACHI: Sindh Governor Mohammad Zubair said on Friday that Pakistan for the first time is going to use Thar coal for power generation, as a single unit of 660 megawatts (2x330MW), expected to start supplying power to the national grid from next year.

Speaking at an interactive session held by the Sindh Engro Coal Mining Company (SECMC) at the Governor House, he said there is going to be a combined investment of $4.5 billion, which is not restricted to only coal mining, but about transforming the entire landscape of the area.

He said that Thar, being amongst the poorest and most neglected parts of the country, will hopefully be transformed through this economic activity.

Engro Powergen CEO Shamsuddin Ahmed Shaikh, speaking on the occasion said that Thar coal excavation work has been completed up to 114 metres, and the balance of 26 metres would be completed by October 2018. Thereafter, the first unit of 660MW will start generating power by December 2018. The original completion period of the project, he said, is 42 months, but it is hoped it would be completed in 38 months.

Mr Shaikh said that the combined investment in coal mining and power projects stands at around $2bn, with $845 million for mining, and around $1.1bn for power project.

Thar coal’s feasibility report was approved, but when Engro took the project, there was a sudden fall in the world commodity prices including coal, owing to which, at one stage, Engro almost faced bankruptcy, Mr Shaikh recalled.

“However, after the ground-breaking in April 2016, there was no looking back. Work progressed ahead of schedules and today we proudly announce that the first-ever power generating unit fueled by indigenous coal of Thar will be operational next year,” he said.

He optimistically added that Thar has the potential to transform Pakistan in fulfilling its energy needs at a very cheap rate.

Mr Shaikh lauded the role and assistance extended by both provincial and federal governments in bringing their dream project to life.

Responding to a question, he said it is a China-Pakistan Economic Corridor project and has the potential to export energy to India, which has almost exhausted its coal reserves running in the same belt of Thar on their side.

In response to this, the governor said there is always economic loss for not doing business with our neighbours and the time is right to initiate talks with India for coal and power supply.

“All the industrial states of India, bordering Pakistan are energy-deficient and in bad need of cheap, sustainable power supply,” he added.

Shamsuddin Ahmed Sheikh said the Engro ensured to engage Thar’s local people, recognising the fact that first right over resources vests with indigenous people.

The company has also opened schools, health clinics and launched housing schemes in the area.

Published in Dawn, December 30th, 2017

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Judiciary’s SOS
Updated 28 Mar, 2024

Judiciary’s SOS

The ball is now in CJP Isa’s court, and he will feel pressure to take action.
Data protection
28 Mar, 2024

Data protection

WHAT do we want? Data protection laws. When do we want them? Immediately. Without delay, if we are to prevent ...
Selling humans
28 Mar, 2024

Selling humans

HUMAN traders feed off economic distress; they peddle promises of a better life to the impoverished who, mired in...
New terror wave
Updated 27 Mar, 2024

New terror wave

The time has come for decisive government action against militancy.
Development costs
27 Mar, 2024

Development costs

A HEFTY escalation of 30pc in the cost of ongoing federal development schemes is one of the many decisions where the...
Aitchison controversy
Updated 27 Mar, 2024

Aitchison controversy

It is hoped that higher authorities realise that politics and nepotism have no place in schools.