Corridor projects reprioritised, not changed: govt

Published February 20, 2015
Flags of Pakistan and China.—Reuters/File
Flags of Pakistan and China.—Reuters/File
Road on a mountain.—White Star/File
Road on a mountain.—White Star/File

ISLAMABAD: Amid the ongoing controversy over the route of the China-Pakistan Economic Corridor (CPEC), the government on Thursday assured a Senate panel that energy projects of the multibillion dollar flagship programme were not changed, but prioritised in a phased manner.

Briefing the Senate Standing Committee on Water and Power, Water and Power Secretary Younas Dagha said there was no change in the energy projects which were being set up in all the four provinces and Azad Jammu and Kashmir.

He also told the committee that the Neelum-Jhelum Hydropower Project still faced a shortage of $470 million and that the 425mw Nandipur Combined Cycle Project would be completed by June 30 this year.

Know more: Analysis: China-Pakistan corridor or labyrinth?

The meeting was chaired by committee chairman Zahid Khan of the Awami National Party (ANP), who recommended the termination of contracts for Golen Gol Hydropower Project in Khyber Pakhtunkhwa after alleging irregularities in its bidding and award of contract process.

Mr Dagha said coal-based power projects were planned in all the four provinces but their development had been divided into two phases. In the first phase, only those projects which could be completed in three to four years had been prioritised, such as Thar, Port Qasim and Sahiwal. These are also projects that will use local coal given the capacity constraints of Pakistan Railways as well as the ports.

He explained that only one 1320mw coal-based project at Sahiwal had been prioritised because Pakistan Railways had the capacity to transport coal only for this project at this early stage. Railways would need to augment its capacity with additional bogies and locomotives to transport coal for additional power plants.

Therefore, the government has decided to take only those projects in the first phase which could be developed without any additional investment.

In the second phase, the government plans to set up more power projects at Thar, Hub, Gwadar, Kallar Kahar, Muzaffargarh, Rahimyar Khan and in KP. Moreover, Gadani Coal Power Park project would be initiated after completion of the feasibility study. He said that Engro’s coal power project in Thar was expected to achieve financial closure by April this year.

He said the coal-based power projects could attract only Chinese investment and hence Chinese private investors were coming up for coal power projects without any government investment.

Responding to a question, Water and Power Development Authority (Wapda) Chairman Zafar Mahmood said the strategic Neelum-Jhelum project in AJK was still facing a $470 million funding shortage and the federal government would revise the project documents (PC-1) of the project that could further increase its cost from previous estimates of Rs275 billion.

He said the project could be delayed beyond November 2016 if necessary funds were not made available in time. He said a revised PC-1 of the project was being finalised for approval of the project because even the previous cost revision from Rs84 billion to Rs275 billion after the earthquake had not taken into account various taxes and duties and other unseen expenses. He said the revision could further escalate the project cost.

Published in Dawn, February 20th, 2015

On a mobile phone? Get the Dawn Mobile App: Apple Store | Google Play

Opinion

Editorial

Ties with Tehran
Updated 24 Apr, 2024

Ties with Tehran

Tomorrow, if ties between Washington and Beijing nosedive, and the US asks Pakistan to reconsider CPEC, will we comply?
Working together
24 Apr, 2024

Working together

PAKISTAN’S democracy seems adrift, and no one understands this better than our politicians. The system has gone...
Farmers’ anxiety
24 Apr, 2024

Farmers’ anxiety

WHEAT prices in Punjab have plummeted far below the minimum support price owing to a bumper harvest, reckless...
By-election trends
Updated 23 Apr, 2024

By-election trends

Unless the culture of violence and rigging is rooted out, the credibility of the electoral process in Pakistan will continue to remain under a cloud.
Privatising PIA
23 Apr, 2024

Privatising PIA

FINANCE Minister Muhammad Aurangzeb’s reaffirmation that the process of disinvestment of the loss-making national...
Suffering in captivity
23 Apr, 2024

Suffering in captivity

YET another animal — a lioness — is critically ill at the Karachi Zoo. The feline, emaciated and barely able to...