Lack of funds hampers reconstruction in quake-hit areas

Published January 27, 2015
Rescue workers gather at the site of a building collapse in Muzaffarabad. — Reuters/file
Rescue workers gather at the site of a building collapse in Muzaffarabad. — Reuters/file

ISLAMABAD: Rehabilitation and reconstruction projects started in the wake of the 2005 earthquake have not been completed yet because of shortage of funds.

This was said by an official of the Earthquake Reconstruction and Rehabilitation Authority (Erra) at a meeting of the National Assembly’s Standing Committee on Kashmir Affairs and Gilgit-Baltistan held at the Parliament House on Monday with Malik Ibrar in the chair

The Erra representative said that 68 per cent of projects had been completed and handed over to the relevant authorities. The rest of the projects had been delayed because of non-availability of funds, he added.

The earthquake left over 73,000 people dead and 128,304 injured, besides razing to ground 600,000 houses and 5,808 educational institutions. The material losses were worth an estimated Rs125.2 billion.

The committee recommended to the Finance Division to immediately release the needed funds to Erra for an early restoration of quake-devastated areas. The committee noted that since most of the funds came from international donors, it was necessary to spend them on rehabilitation and reconstruction works without fail.

MNAs Tahir Iqbal, Mian Imtiaz Ahmad and Molvi Agha Mohammad and senior officials from the Ministry of Kashmir Affairs and Gilgit-Baltistan attended the meeting.

Published in Dawn, January 27th, 2015

On a mobile phone? Get the Dawn Mobile App: Apple Store | Google Play

Opinion

Editorial

Judiciary’s SOS
Updated 28 Mar, 2024

Judiciary’s SOS

The ball is now in CJP Isa’s court, and he will feel pressure to take action.
Data protection
28 Mar, 2024

Data protection

WHAT do we want? Data protection laws. When do we want them? Immediately. Without delay, if we are to prevent ...
Selling humans
28 Mar, 2024

Selling humans

HUMAN traders feed off economic distress; they peddle promises of a better life to the impoverished who, mired in...
New terror wave
Updated 27 Mar, 2024

New terror wave

The time has come for decisive government action against militancy.
Development costs
27 Mar, 2024

Development costs

A HEFTY escalation of 30pc in the cost of ongoing federal development schemes is one of the many decisions where the...
Aitchison controversy
Updated 27 Mar, 2024

Aitchison controversy

It is hoped that higher authorities realise that politics and nepotism have no place in schools.