Partial flow begins from Zarghun gas field

Published September 3, 2014
— File photo
— File photo

ISLAMABAD: A gas field discovered in Balochistan in 1998 and abandoned for poor economics has started partial flows into the system.

An official of Mari Gas Company which operates the field told Dawn that the gas field was required to achieve full load supply of 20 million cubic feet per day (MMCFD) before November 30, 2014 under the agreement.

The field has estimated reserves of about 77 billion cubic feet (BCF), and may last for 15 years at production level of 20 MMCFD. However, the commercial life of the field could decline when production touches 4-5 MMCFD or increase if gas pressure remains intact and go up with more finds.

The official said the company was currently contributing gas to the national transmission system on trial basis under an interim commissioning period during which gas supplies are made without specifications agreed and quantities committed.

This means the gas quality and quantities can fluctuate during the testing phase and production price is about 30 per cent cheaper for three months.

An international consortium led by Premier Kufpec the United Kingdom had discovered gas reserves at Zarghun South-1 well followed by another well (Zarghun South-II) in 2000 but abandoned its development due to poor commercial viability involving $34 million cost and over 64-kilomter pipeline through rugged terrain required to link the well to main transmission system near Quetta.

A new consortium led by Mari Petroleum took over the field in October 2003 and attempted to hire engineering, procurement and construction (EPC) contractors but even the reduced cost of $31 million for a refurbished dehydration and purification plant could not transform the project commercially viable.

An in-house arrangement without recourse to EPC contract, however, resulted in setting up of gas gathering, purification and dehydration plant at a cost of $21 million. Under a gas sales and purchase agreement of September 2013 with Sui Southern Gas Company Limited (SSGCL), the gas field has to achieve commercial operations by November 30, 2014 with 20 MMCFD supplies.

Led by Mari Petroleum, Jura Energy of Canada and Government Holdings Limited is the joint venture operators of the Zarghun South Field in Balochistan.

About 60 BCF out of total 77 BCF reserves at Zarghun South field are described as tight gas, attracting production price of about $6.75 per MMBTU (million British Thermal Unit). It has an attractive heating value of about 900 BTU (British Thermal Unit).

The field spreads over 120 square kilometer of Bolan block area in Sulaiman Fold and Thrust Belt of Middle Indus Basin, about 64 kilomters off Quetta.

Published in Dawn, September 3rd, 2014

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Ties with Tehran
Updated 24 Apr, 2024

Ties with Tehran

Tomorrow, if ties between Washington and Beijing nosedive, and the US asks Pakistan to reconsider CPEC, will we comply?
Working together
24 Apr, 2024

Working together

PAKISTAN’S democracy seems adrift, and no one understands this better than our politicians. The system has gone...
Farmers’ anxiety
24 Apr, 2024

Farmers’ anxiety

WHEAT prices in Punjab have plummeted far below the minimum support price owing to a bumper harvest, reckless...
By-election trends
Updated 23 Apr, 2024

By-election trends

Unless the culture of violence and rigging is rooted out, the credibility of the electoral process in Pakistan will continue to remain under a cloud.
Privatising PIA
23 Apr, 2024

Privatising PIA

FINANCE Minister Muhammad Aurangzeb’s reaffirmation that the process of disinvestment of the loss-making national...
Suffering in captivity
23 Apr, 2024

Suffering in captivity

YET another animal — a lioness — is critically ill at the Karachi Zoo. The feline, emaciated and barely able to...